Community Update
September 2026
As the YarraBend community continues to grow, we’re pleased to share the latest updates across our neighbourhood, including progress on new parks, amenities and residential developments.
There’s plenty happening throughout the precinct, with new public spaces taking shape and construction continuing across a number of residential projects.


Landscaping Underway
Paper Square Park
Works continue at Paper Square Park, with civil works complete and landscaping now underway across the future park.
The first playground structures have also been installed, providing an early look at the recreational spaces that will soon be available for the community.

Design Complete
Heritage Park
The design for Heritage Park has been finalised and submitted to Yarra Council for review.
Presentation of the design to the Community Reference Group is anticipated in mid-October as the project progresses through the next stage of planning.

Construction Update
Parkview Townhouses
Construction at Parkview Townhouses is moving into its final stages, with scaffolding removed from the northern side of the development and internal finishing works continuing throughout the homes.
Works to the surrounding laneway are also progressing, with further activity scheduled in the coming months.

Construction Update
The Guild
Progress continues at The Guild, with window installation complete for Buildings A and B and scaffolding now being removed from Building A.
Internal fit-out works are advancing across the development as construction continues through the remaining buildings.

Construction Update
Boiler House & Glass House
Early construction works at Boiler House & Glass House continue to advance, with excavation nearing completion and the first tower crane now installed on site.
Ground services are underway ahead of the next phase of structural works.